Operation
and management of electricity infrastructure is one of the programs to
realize Papua Bright Up in 2019. PLN WP2B has four courses and one goal
for the realization of Papua Bright Up of 2019. First, electrify 14
districts in Papua and West Papua in 2016 to 2017. Later , electrify
village districts or districts with a ratio of electrified PLN 100
percent in 2019 and the ratio of electrified villages PLN 100 percent in
2020.
Furthermore,
to provide electricity for the three outer islands (population) in 2016
to 2017. Then, raise the flame hours of operation at least 18 hours a
day starting in 2016 to 2020. Meanwhile, the main objectives to be
achieved is to increase the electrification ratio up to 90.22 per cent
in the province Papua and West Papua.
Deiyai
in the district, the number of customers who have officially become
customers PLN 155 customers. However, potential customers can increase
up to approximately 750 customers. For diesel engine power plants,
district Deiyai has a power capacity of 2 x 500 kW or 1 MW. In
Yahukimo, the number of potential customers PLN 237 customers with a
number of additional potential customers approximately 1,300 customers.
Yakuhimo power capacity in the system is divided into four with each
capacity of 1 x 800 kVA, 1 x 500 kVA, 1 x 350 kVA, and 1 x 250 kVA.